Forest

Land

  • Impact area: 66 ac
  • State: Virginia
  • USDA Land: Yes

Project milestone

  • 1st Site Control: 12/30/2023
  • Forecast NTP: 2024-Q4
  • Forecasted COD: 2025-Q3

Concept

  • Power: 6.5MWdc / 6.0MWac
  • 1st year Production: 11,646 MWh/yr
  • Specific production 1,788 kWh/kWp/yr
  • Interconnection: Dominion Energy Virginia
  • New Gen-tie line: < 1 miles
  • Offtaker: Dominion Energy Virginia
  • Voltage: 13.2kV

Major equipment

  • PV Modules: Vikram Solar 640Wp, 10,179 pcs
  • Inverter: SMA 3MWac Central, 2pcs
  • Racking: Horizontal Axis N-S tracking